Estimation That Survives Contact with Reality
Three-point estimates, story points, reference class forecasting and the planning fallacy.
On this page
Humans are systematically optimistic about their own plans and reasonably accurate about other people's. Good estimation practice is mostly a set of tricks for exploiting that asymmetry.
Three-point (PERT)
Expected duration = (Optimistic + 4 × Most Likely + Pessimistic) ÷ 6, with standard deviation (P − O) ÷ 6. Report the range, never the single number — a point estimate quoted upward becomes a commitment by Friday.
Relative sizing
- Story points measure size and complexity, not hours. They work because relative comparison is more reliable than absolute prediction.
- Velocity is a forecasting input, not a performance metric. The moment it is used to compare teams, it inflates.
- Use throughput (items per week) when items are of similar size — it needs no estimation at all.
Related PMI standards & templates
External resources on pmi.org — links open in a new tab. Some require PMI membership.
PMI standard templates for this topic
Editable Word and print-ready PDF downloads — no sign-up required.
- Project plan pack template →A PMI standard project plan template pack: the nine-section plan document plus a schedule worksheet with duration, dependency, float and milestone tabs.
- Lessons learned log template →A PMI standard lessons learned log template with a facilitation walkthrough, a worked example and the review cadence that stops lessons being written from memory at closure.
- Sprint planning template →A PMI standard sprint planning template with a capacity calculator, a Definition of Ready check, a two-hour agenda and a worked example of a commitment that fits.
- User story template →A PMI standard user story template with Given/When/Then acceptance criteria, an INVEST check, a fully worked example and the six patterns for splitting a story that is too big.
The PM Delivery Toolkit turns everything in this guide into fill-in templates — $25, one payment.
Get five PM habits that quietly save projects
Baselines, critical path discipline, RAID logs that people read, range estimating and status packs sponsors act on — sent straight to your inbox, free.
One email, no spam, unsubscribe any time.
Discussion
Share how you applied this in practice, ask a question, or add a tip for other readers.
Loading comments…