Critical Path
Dan Sunil monogram
PMI standard template · Word & PDF · Toolkit only

Project Status Report Template (PMI Standard Word & PDF)

6 min read · Reviewed August 2026 by Dan Sunil Kumar

A project status report is the short, repeatable update that tells a sponsor where the work stands, what changed since last time, and what they need to decide. It is written for someone who has ten minutes and no appetite for detail.

One page is the target, two the maximum. Issue it on a fixed cadence — weekly or fortnightly — because a report that appears only when there is bad news trains people to dread it.

PMI standard alignment
Standard followed
PMBOK Guide 7th ed. / PMI Practice Standard for Earned Value Management
Performance domain
Measurement
Process group
Monitoring & Controlling
Knowledge area
Communications Management

The Word & PDF files for this template are part of the paid PM Delivery Toolkit — there is no free download. The full walkthrough, worked example and section guidance below stay open to read.

Get the project status report in the toolkit

When to use it

  • A sponsor or steering group expects a regular written update on delivery.
  • Status is currently communicated verbally, so nobody can trace when a slip was first flagged.
  • Several workstreams need rolling up into one view for governance.
  • A client contract requires periodic reporting on progress, spend and risk.

Every section, and what good looks like

  1. Section 1

    Report header

    Project name, reporting period, project manager, sponsor and the date the report was issued.

    The period is explicit, so a reader can tell a two-week gap from a one-week one.

  2. Section 2

    Overall status (RAG)

    One overall red/amber/green rating, plus separate ratings for schedule, budget, scope and risk.

    Every non-green rating carries a one-line reason and a named recovery action.

  3. Section 3

    Summary for the sponsor

    Three sentences: where we are, what changed this period, what you need to decide.

    It can be read on a phone without opening the tables underneath.

  4. Section 4

    Progress this period

    Deliverables and milestones actually completed, not activity that was merely busy.

    Items are finished things, each traceable to a milestone or acceptance.

  5. Section 5

    Planned next period

    What will be delivered before the next report, with an owner and a date against each item.

    Short enough to be credible, and checked against last report's promises.

  6. Section 6

    Milestones

    Baseline date, current forecast date and status for each key milestone.

    Baseline stays fixed so slippage is visible instead of quietly re-baselined.

  7. Section 7

    Budget

    Approved budget, spend to date, forecast at completion, and the cause of any variance.

    Forecast at completion is stated even when it is uncomfortable.

  8. Section 8

    Key risks and issues

    The few threats and live problems that matter, with impact, owner, action and due date.

    Top five only — the full RAID log stays a separate document.

  9. Section 9

    Decisions needed from the sponsor

    Explicit asks, each with a deadline and the consequence of delay.

    Named decisions, not hints. This is the section that makes the report useful.

  10. Section 10

    Changes since last report

    Approved changes and their effect on scope, cost or dates.

    Cross-references the change request so scope drift has an audit trail.

A filled-in example

A realistic weekly status report for an in-flight delivery project, so you can see how much detail a steering group actually reads.

Worked project status report example
Project nameCustomer onboarding rebuild
Reporting period3 – 14 March
Overall statusAmber — identity vendor integration is two weeks behind.
SummaryPilot build is complete and in test. Vendor API changes cost us two weeks. We need a decision on pilot scope by 21 March.
CompletedDigital application form signed off; 50-customer pilot cohort selected.
Next periodIdentity check integration in staging (A. Rao, 27 March).
MilestonePilot go-live — baseline 14 Jan, forecast 28 Jan, at risk.
Budget£180,000 approved, £96,400 spent, £188,000 forecast — vendor rework.
Decision neededApprove a manual identity check for the pilot only, by 21 March, or go-live moves to April.

Mistakes that make a status report ignored

  • Reporting activity instead of outcomes — a list of meetings attended tells a sponsor nothing.
  • Green until it is suddenly red. Amber exists so slippage can be raised while it is still fixable.
  • Re-baselining milestone dates silently, which hides cumulative slip.
  • Dumping the whole risk register in, so the three risks that matter get lost.
  • No decisions section, which turns the report into an archive rather than a tool.
  • Skipping a cycle when there is nothing good to say — this is exactly when sponsors need it.
Paid toolkit

26 more artifacts, ready to fill in

The PM Delivery Toolkit packages the RAID log, status pack, estimation and earned value workbooks, capacity planner, agile sprint tools and 150 PMP-style questions — Word, Excel and print-ready PDF.

  • Status pack and steering deck with RAG logic built in
  • Estimation and EVM workbook: CPI, SPI and EAC calculated
  • Capacity planner with an over-allocation heatmap
  • Agile set: sprint planning, user stories, retros, backlog, WSJF
What’s inside all 26 artifacts

One payment · lifetime updates · 14-day refund. Files unlock on your download page as soon as payment clears.

Questions people ask

What should a project status report include?
A header with the reporting period, an overall RAG rating with separate schedule, budget, scope and risk ratings, a three-sentence summary, progress this period, plans for next period, milestone baseline versus forecast, budget and forecast at completion, top risks and issues, decisions needed from the sponsor, and approved changes since the last report.
How often should you send a project status report?
Weekly for active delivery, fortnightly for slower or long-running work, and monthly only for programmes reporting to a board. Pick a cadence and hold it — irregular reporting is read as a warning sign.
What do red, amber and green actually mean?
Green means the project will hit its committed dates, budget and scope with the plan in place. Amber means it will not without intervention, and the intervention is named. Red means a commitment has already been broken or cannot be recovered inside current tolerances.
How long should a status report be?
One page, two at most. If governance needs more depth, attach the milestone plan or RAID log as annexes and keep the report itself skimmable in five minutes.
What is the difference between a status report and a dashboard?
A dashboard shows current metrics, usually generated from your delivery tool. A status report adds interpretation: why the numbers moved, what you are doing about it, and what you need the sponsor to decide.

Read next

Other PMI-standard templates

Every one has the same walkthrough, worked example and PMI mapping, and every file ships inside the PM Delivery Toolkit.

Keep going on the site

The hubs and tools that pair with this project status report.

Free tips

Get five PM habits that quietly save projects

Baselines, critical path discipline, RAID logs that people read, range estimating and status packs sponsors act on — sent straight to your inbox, free.

One email, no spam, unsubscribe any time.