Critical Path
Dan Sunil monogram
Back to library
Abstract risk matrix grid with blue and amber severity cells
Risk matrix

Likelihood × impact drives the response

Risk & Quality

Earned Value: Measuring Progress in Money

PV, EV, AC and the four formulas that tell you whether the project is genuinely on track.

7 min readAdvanced#evm#metrics#control
On this page

Percent-complete reporting is self-assessed and therefore useless. Earned value replaces opinion with a single currency for scope, schedule and cost.

TermMeaning
PV — Planned ValueBudgeted cost of work scheduled to date
EV — Earned ValueBudgeted cost of work actually completed
AC — Actual CostWhat has really been spent
BAC — Budget at CompletionTotal approved budget

The four numbers that matter

  • Schedule Variance = EV − PV. Negative means behind.
  • Cost Variance = EV − AC. Negative means over budget.
  • SPI = EV ÷ PV. Below 1.0 means behind.
  • CPI = EV ÷ AC. Below 1.0 means every pound buys less than planned.

Related PMI standards & templates

External resources on pmi.org — links open in a new tab. Some require PMI membership.

Skip the blank page

The PM Delivery Toolkit turns everything in this guide into fill-in templates — $25, one payment.

See the toolkit
Free tips

Get five PM habits that quietly save projects

Baselines, critical path discipline, RAID logs that people read, range estimating and status packs sponsors act on — sent straight to your inbox, free.

One email, no spam, unsubscribe any time.

Share LinkedIn

Discussion

Share how you applied this in practice, ask a question, or add a tip for other readers.

Loading comments…