Resource & Capacity Planning That Holds Up

Match demand to real availability, expose over-allocation early, and level the plan before the team burns out.

6 min readPractitioner#resources#capacity#levelling
On this page

Most late projects were never resourced honestly. The schedule assumed eight productive hours a day from people who also run support, attend governance meetings and take leave. Capacity planning is the discipline of planning against the hours that actually exist.

Start from real availability

  1. 1List every named person and their contracted hours for the period.
  2. 2Subtract non-project load: leave, training, support rota, line management, company meetings.
  3. 3Apply a productivity factor — 65–80% of remaining time is realistic for focused delivery work.
  4. 4Only then assign activities, and compare the total demand per person per week to that net number.
InputTypical figureWhy it matters
Gross weekly hours40The number stakeholders assume you have
Leave & holidays-3Averaged across the year, not ignored until it happens
Meetings & admin-6Ceremonies, governance, email, approvals
Productivity factor×0.75Context switching and unplanned interrupts
Net project capacity≈23 hrsThe only number worth scheduling against

Spot over-allocation before it bites

  • Anyone above 100% of net capacity in any week is a schedule risk, not a stretch goal.
  • Watch the specialists: a single-point-of-failure skill will quietly become your critical path.
  • Peaks that cluster at phase boundaries usually mean the plan front-loads reviews and approvals.
  • Check the same person is not committed to two projects at 80% each.

Levelling vs. smoothing

TechniqueWhat it changesEffect on end date
Resource levellingDelays activities until people are freeEnd date can move out
Resource smoothingUses float only, keeps the critical path intactEnd date holds
Fast trackingRuns activities in parallelShortens, raises rework risk
CrashingAdds people or overtimeShortens, raises cost

Make it visible

  • Publish a one-page heat map of person-by-week allocation and review it in every steering meeting.
  • Escalate demand that exceeds supply as a decision, not a complaint: cut scope, move the date, or add capacity.
  • Re-forecast capacity monthly — attrition, onboarding ramp-up and reorganisations all invalidate the sheet.
  • Record actual hours against planned; the gap is your productivity factor for the next project.

PMI standard templates for this topic

Editable Word and print-ready PDF downloads — no sign-up required.

  • RACI matrix template →A PMI standard RACI matrix template with a section-by-section walkthrough, a filled-in example and the one-accountable-owner rule that stops responsibility arguments.
  • Sprint planning template →A PMI standard sprint planning template with a capacity calculator, a Definition of Ready check, a two-hour agenda and a worked example of a commitment that fits.
Skip the blank page

The PM Delivery Toolkit turns everything in this guide into fill-in templates — $25, one payment.

See the toolkit
Free tips

Get five PM habits that quietly save projects

Baselines, critical path discipline, RAID logs that people read, range estimating and status packs sponsors act on — sent straight to your inbox, free.

One email, no spam, unsubscribe any time.

Share LinkedIn

Discussion

Share how you applied this in practice, ask a question, or add a tip for other readers.

Loading comments…